Decision details
Redevelopment of Dunstable Leisure Centre and Library
Decision Maker: EXECUTIVE
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To approve undertaking the procurement of a
building contractor to redevelop Dunstable Leisure Centre
Decision:
RECOMMENDED to Council
That an additional £3.519m be allocated to implement the redevelopment of Dunstable Leisure Centre and Library in accordance with the revised option 7. (Note: this additional expenditure is included within the Capital Programme being recommended to Council elsewhere on this agenda).
RESOLVED
That officers actively seek to meet the additional £3.519m requirement through new sources of funding or from within the existing capital budget in order to create no net increase in capital requirements during the period of the plan.
Report author: Jill Dickinson
Publication date: 11/02/2016
Date of decision: 09/02/2016
Decided at meeting: 09/02/2016 - EXECUTIVE