June 2015 – Q1 Capital Budget Monitoring Report

Decision Maker: EXECUTIVE

Decision status: For Determination

Is Key decision?: No

Is subject to call in?: No

Purpose:

The report provides information on the projected capital outturn for 2015/16 as at June 2015.

Decision:

1.      That the forecast position which is to spend £128.3M (£128.3M in February) compared to the budget of £138.3M, be noted.  The variance of £10.3M (£10.3M in February) includes proposed deferred spend of £7.8M.

2.      That the virement of £2.437M from the Household Recycling and Waste Centre redevelopment project to the Thorn Turn waste park and also the Depot and Salt Barn – North project, as set out in paragraph 19e, be approved.

Report author: Denis Galvin

Publication date: 06/08/2015

Date of decision: 04/08/2015

Decided at meeting: 04/08/2015 - EXECUTIVE