Decision details
Flitwick Leisure Centre
Decision Maker: EXECUTIVE
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To consider approving a budget for project management and design team services so that the Council can consider the feasibility of delivering a new leisure centre in Flitwick.
Decision:
1. That in accordance with the Council’s Code of Procurement Governance and the procurement strategy set out in paragraphs 22 – 30 in the report, procurement of consultancy support for project management and design team services be approved.
2. That the use of funding from existing schemes within the Capital Programme be approved as set out in paragraph 7 of the report.
Publication date: 17/05/2013
Date of decision: 14/05/2013
Decided at meeting: 14/05/2013 - EXECUTIVE
Accompanying Documents: