December 2013 - Quarter 3 Capital Budget Monitoring Report

Decision Maker: EXECUTIVE

Decision status: Recommendations approved

Is Key decision?: No

Is subject to call in?: Yes

Purpose:

To consider the revenue, capital and HRA quarter 3 budget monitoring report.

Decision:

1.      That the overall forecast position to spend £73.7m compared to the budget of £94.6m be noted.  This is a variance of £20.9m as a result of an overspend of £4.4m and the proposed deferred spend to 2014/15 of £25.3m.

2.      To request officers to carefully examine their forecast spend to determine how realistic the proposals to defer spend into 2014/15 are.

Publication date: 20/03/2014

Date of decision: 18/03/2014

Decided at meeting: 18/03/2014 - EXECUTIVE

Effective from: 28/03/2014