Decision details

Decision details

September 2015 Quarter 2 Capital Budget Monitoring

Decision Maker: EXECUTIVE

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

The report provides information on the projected capital outturn for 2015/16 as at September 2015. It excludes the Housing Revenue Account which is subject to a separate report.

Decision:

1.      That the gross forecast which is below budget by £30.2m (£19m at period 6 last year against a lower budget of £116.8m) and the net forecast which is £21.5m below budget be noted.

2.      That a virement for £3.360m from HWRC Redevelopment project to the Thorn Turn Waste Park, Depot South and Depot and Salt Barn North Schemes be approved.

 

Report author: Denis Galvin

Publication date: 04/12/2015

Date of decision: 01/12/2015

Decided at meeting: 01/12/2015 - EXECUTIVE

Accompanying Documents: