Urgent Item of Business - Draft Local Plan for Central Bedfordshire

Meeting: 10/10/2017 - EXECUTIVE (Item 62)

62 Urgent Item of Business - Central Bedfordshire Local Plan pdf icon PDF 94 KB

 

This report provides an update on the schedule for the next phase of public engagement on the Central Bedfordshire Local Plan and the programme to achieve submission of the Local Plan to the Secretary of State by 31 March 2018.

Additional documents:

Decision:

That the revised timetable, as set out in Appendix A to the report, for the development of the Central Bedfordshire Local Plan be endorsed.

Minutes:

 

The Executive considered a report from the Executive Member for Regeneration that proposed the next phase of public engagement on the Central Bedfordshire Local Plan and the programme to achieve submission of the Plan to the Secretary of State by 31 March 2018. 

 

In response to a question, the Head of Strategic Growth explained that the Government had published its consultation on the methodology for determining the level of housing need.  The housing need figure for Central Bedfordshire was 2553 homes per annum based on the proposed methodology, representing a 60% increase on the Council’s current objectively assessed need (ONA) of 1600 homes per annum. 

 

In response to a question, the Executive Member for Regeneration explained that if the Council did not have a Local Plan developers could apply for planning permission on small developments.  These small developments would not produce the financial contribution required to fund major infrastructure.

 

Reason for decision:  The revised timetable would accelerate the process for submitting the Local Plan to provide a firm foundation for sustainable growth in Central Bedfordshire.

 

RESOLVED

 

that the revised timetable, as set out in Appendix A to the report, for the development of the Central Bedfordshire Local Plan be endorsed.

 

The decision was unanimous.